K. Male'
|
15 Feb 2024 | Thu 16:00
N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project
N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project
MTCC
Manadhoo Harbor Channel Dredging Project
Manadhoo harbor channel dredging, breakwater construction progressing
The project is valued at MVR 39.13 million
MTCC noted that the component of concrete bridge construction, is nearing completion
Currently ongoing are the bar bending and concrete work

The harbor channel dredging and breakwater construction project in Manadhoo island of Noonu atoll is well underway.

This was revealed by the Maldives Transport and Contracting Company (MTCC) on Thursday.

As such, providing the latest updates of the Manadhoo harbor channel dredging and breakwater construction project via social media platform ‘X’, MTCC revealed that the project is well underway.

MTCC revealed that they recently completed the jetty column installation work. This component of the project had reached 70 percent progress by January 4, and has been completed by mid-February.

Currently ongoing are the bar bending and concrete work.

Further, MTCC noted that the component of concrete bridge construction, is nearing completion.

The project had reached overall 75 percent progress by November 2023. MTCC revealed that the construction of the ramp and revetment, were completed that month.

The company completed the channel breakwater operations and construction of ramp in July.

Under the scope of the project, MTCC is required to conduct dredging and excavation operations in an area measuring 13,216 cubic meters and entrance channel dredging operations in an area spanning 17,450 cubic meters.

The project also entails the construction of a 183-meter breakwater, a 188-meter revetment, a concrete bridge measuring 4.5 meters in width and 244 meters in length and a ramp measuring 10 meters by 10 meters.

The company will also construct a 244-meter jetty and a concrete jetty on the south side, measuring 105 meters by five meters.

Other work that comes under the scope of the project includes the installation of navigational aids and mooring buoys.

The Manadhoo harbor channel dredging and breakwater construction project is valued at MVR 39.13 million.

The project was contracted to MTCC by the former administration’s Ministry of National Planning, Housing and Infrastructure.

Last updated at: 7 months ago
Reviewed by: Maryam Dhaanish Nasheed
- comment