Sh. Maaungoodhoo Harbor Development Project
Sh. Maaungoodhoo Harbor Development Project
MTCC
Maaungoodhoo harbor development project
Maaungoodhoo harbor development project reaches 55 percent progress
The project is valued at MVR 56.79 million
The project also entails the installation of a harbor pavement
The company commenced the breakwater profiling component of the project on February 11

The harbor development project in Maaungoodhoo island of Shaviyani atoll has reached overall 55 percent progress.

This was revealed by the Maldives Transport and Contracting Company (MTCC) on Thursday.

As such, taking to social media platform ‘X’ to provide the latest updates of the Maaungoodhoo harbor development project to the public, MTCC revealed that the project is well underway.

MTCC most recently completed the construction of a quay wall block, under the project.

They delivered all rock boulders required for the project in January.

The company commenced the breakwater profiling component of the project on February 11.

Under the scope of the project, MTCC is required to conduct dredging operations in an area measuring 59,013 cubic meters and channel dredging operations in an area measuring 3,245 cubic meters.

The construction of a ramp, a concrete jetty, a breakwater measuring 362 meters, a quay wall measuring 312 meters and a 105-meter revetment also comes under the scope of the project.

The project also entails the installation of a harbor pavement measuring 1,509 square meters, harbor lights as well as mooring buoys.

The Maaungoodhoo harbor development project is valued at MVR 56.79 million.