localManadhoo Harbor Channel Dredging Project

Manadhoo harbor channel dredging, breakwater construction well underway

3 ޖެނުއަރީ 2024 | ބުދަ 19:36

The project was contracted to MTCC by the Ministry of National Planning, Housing and Infrastructure

ޒުނާނާ ޒާލިފް
Zunana Zalif | 3 ޖެނުއަރީ 2024 | ބުދަ 19:36
N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project

N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project | MTCC

The harbor channel dredging and breakwater construction project in Manadhoo island of Noonu atoll is progressing well.

This was revealed by the Maldives Transport and Contracting Company (MTCC) on Wednesday.

As such, providing the latest updates of the Manadhoo harbor channel dredging and breakwater construction project via social media platform ‘X’, MTCC revealed that the project is well underway.

MTCC revealed that currently ongoing is the jetty construction component, which has reached 70 percent completion.

Further, the company is carrying out work for bed preparation to install jetty columns.

The project had reached overall 75 percent progress by November 2023. MTCC revealed that the construction of the ramp and revetment, were completed that month.

The company completed the channel breakwater operations and construction of ramp in July.

Under the scope of the project, MTCC is required to conduct dredging and excavation operations in an area measuring 13,216 cubic meters and entrance channel dredging operations in an area spanning 17,450 cubic meters.

The project also entails the construction of a 183-meter breakwater, a 188-meter revetment, a concrete bridge measuring 4.5 meters in width and 244 meters in length and a ramp measuring 10 meters by 10 meters.

The company will also construct a 244-meter jetty and a concrete jetty on the south side, measuring 105 meters by five meters.

Other work that comes under the scope of the project includes the installation of navigational aids.

The Manadhoo harbor channel dredging and breakwater construction project is valued at MVR 36.94 million.

The project was contracted to MTCC by the Ministry of National Planning, Housing and Infrastructure.

N. ManadhooMTCCMaldives Transport and Contracting Company

Popular

1

Nine-year-old child injured in Hulhumalé accident, passes away

2

Another road accident leaves 17-year-old girl injured

3

"My beloved little heart! my dear child!": Ashraf’s poignant poem on little Zeeva’s passing moves many to tears

4

A detached presidency mocks a starving nation on the brink

5

Government launches project to develop dedicated island for cats

More from Raajje.mv

06 އޯގަސްޓު 2026

Repairs on final segment of Ameenee Magu, which was damaged shortly after being paved by the current administration, scheduled for completion by November

06 އޯގަސްޓު 2026
Repairs on final segment of Ameenee Magu, which was damaged shortly after being paved by the current administration, scheduled for completion by November
05 އޯގަސްޓު 2026

MTCC Reportedly Uses Manual Tools for F. Feeali Futsal Pitch Construction

05 އޯގަސްޓު 2026
MTCC Reportedly Uses Manual Tools for F. Feeali Futsal Pitch Construction
05 އޯގަސްޓު 2026

Work on Mulah cold storage facility comes to a standstill, no progress beyond land clearing since change of gov't

05 އޯގަސްޓު 2026
Work on Mulah cold storage facility comes to a standstill, no progress beyond land clearing since change of gov't
04 އޯގަސްޓު 2026

MTCC fined following missed financial reporting deadlines

04 އޯގަސްޓު 2026
MTCC fined following missed financial reporting deadlines
04 އޯގަސްޓު 2026

MTCC fined for failure to submit financial statements

04 އޯގަސްޓު 2026
MTCC fined for failure to submit financial statements
02 އޯގަސްޓު 2026

MTCC Taxis Accused of Violating Regulations by Picking Up Street Hails and Charging Tourists in USD!

02 އޯގަސްޓު 2026
MTCC Taxis Accused of Violating Regulations by Picking Up Street Hails and Charging Tourists in USD!
31 ޖުލައި 2026

Swell surges cause extensive damage to Gaadhiffushi as harbor construction remains stalled

31 ޖުލައި 2026
Swell surges cause extensive damage to Gaadhiffushi as harbor construction remains stalled
30 ޖުލައި 2026

Newly developed section of Male' Boduthakurufaanu Magu opens without drainage system!

30 ޖުލައި 2026
Newly developed section of Male' Boduthakurufaanu Magu opens without drainage system!
30 ޖުލައި 2026

Work on the Naalaafushi Fitness Center grinds to a halt as the contractor remains unpaid!

30 ޖުލައި 2026
Work on the Naalaafushi Fitness Center grinds to a halt as the contractor remains unpaid!
27 ޖުލައި 2026

M. Naalaafushi Reclamation: Boundary Wall Erodes, Sinks After Completion

27 ޖުލައި 2026
M. Naalaafushi Reclamation: Boundary Wall Erodes, Sinks After Completion
ރާއްޖެދުނިޔެކުޅިވަރުވިޔަފާރި - އިގްތިސާދުސިއްހަތުރިޕޯޓުފިލްމް - މިޔުޒިކްތަފާތު ޚަބަރުއިސްލާމްލައިފް ސްޓައިލް
RaajjeMV
RaajjeTV
Raajje Sport
RaajjeTV Live
RaajjeTV PR
RaajjeMV
Raajje.mv

Copyright © 2010-2025 Raajje Television Pvt Ltd.

All rights reserved

ޕްރައިވެސީ ޕޮލިސީކިޔުންތެރިންގެ ހިޔާލުޓާމްސް އޮފްޔޫސް