K. Male'
|
15 Mar 2022 | Tue 18:45
Design and build of ADh. Hangnaameedhoo harbor development project
Design and build of ADh. Hangnaameedhoo harbor development project
MTCC
MTCC development projects
ADh. Hangnaameedhoo harbor development project reaches 72 percent progress
The project is valued at MVR 29.1 million
The Ministry of National Planning, Housing and Infrastructure contracted the project to MTCC on 29 December 2019, to be completed within 300 days.
The fifth shipment or precast concrete blocks required for quay wall construction was delivered to the site of the project on Sunday
f

The Design and build of ADh. Hangnaameedhoo harbor development project has reached 72 percent progress.

Maldives Transport and Contracting Company (MTCC) revealed that the work to design and build the harbor of Hangnaameedhoo island in Alif Dhaal island is well underway.

As such, the fifth shipment or precast concrete blocks required for quay wall construction was delivered to the site of the project on Sunday.

Design and build of ADh. Hangnaameedhoo harbor development project - MTCC

Under the scope of the project, MTCC is required to dredge and excavate 6,363.1 cubic meters, construct a breakwater measuring 204 meters and a quay wall measuring 266 meters.

Further, the company is also required to install a pavement measuring 1,330 square meters, a revetment stretching up to 160 meters and streetlights.

The project is valued at MVR 29.1 million

The Ministry of National Planning, Housing and Infrastructure contracted the project to MTCC on 29 December 2019, to be completed within 300 days.