MTCC wrapped up the Maritime Survival Center Project earlier this week
MTCC wrapped up the Maritime Survival Center Project earlier this week
MTCC
Maritime Survival Center Project
MTCC wraps up Maritime Survival Center project
A ramp measuring 4.2 meters by four meters was also built
The project was valued at MVR 6.50 million
The project also entailed the installation of a harbor pavement measuring 264.32 square meters

The Maritime Survival Center project has been wrapped up.

This was revealed by the Maldives Transport and Contracting Company (MTCC) on Monday.

As such, providing the latest updates of the Maritime Survival Center project to the public via a post on social media platform ‘X’, MTCC revealed that they successfully completed the project on Monday.

Under the scope of the project, MTCC conducted landfilling works in an area spanning 1,200 cubic meters and sheet pile quay wall construction in a 62.25-meter area.

Further, a ramp measuring 4.2 meters by four meters was also built.

The project also entailed the installation of a harbor pavement measuring 264.32 square meters.

MTCC also installed harbor lights and mooring bollards under the scope of the project.

Further, davit system installation work was also carried out, with two lifeboats and container modifying work.

The Maritime Survival Center project was valued at MVR 6.50 million.