Maldives Transport and Contracting Company (MTCC) has disclosed that the work on design and build of R. Kinolhas Harbor Development Project is well underway.
MTCC states that overall 60 percent of the Kinolhas Harbor Development Project is completed. As such, the company highlights the completion of channel dredging operations under the project.
MTCC is doing dredging and excavation operations under the project.
Additionally, the company will be be doing construction work of a 162m groyne, a 285m breakwater, a 65m revetment, a 186m quay wall and a ramp.
MTCC will also be doing installation of a 1663.36sqm harbor pavement, navigational aids and harbor lights.
The value of the project is MVR 45.1 million.