Madaveli Land Reclamation Project: Only 300 feet reclaimed so far!
21 ނޮވެމްބަރު 2026 | ހޮނިހިރު 17:09Public concern is mounting over the slow progress of the second phase of the land reclamation and coastal protection project in GDh. Madaveli, despite the contract being awarded to MTCC. The 174 million MVR project, which aims to reclaim 19 hectares of land, is considered a vital initiative to provide a permanent solution to the island's long-standing housing crisis.


Madaveli Land Reclamation Project: Only 300 feet reclaimed so far! | MTCC
Ibrahim Nafiz, the MDP National Council President for the Madaveli constituency, has expressed concern over the lack of progress on the GDh. Madaveli land reclamation project.
Expressing his concerns on RaajjeTV’s "Vaudhunaama" program, Nafiz stated that President Dr. Mohamed Muizzu had made numerous pledges to the island of Madaveli. He noted that a land reclamation project was specifically launched in Madaveli to coincide with the recent local council elections.
A sand pump, typically used for beach nourishment at resorts, was brought in under the guise of land reclamation. To date, only a 300-foot area has been reclaimed. Despite this minimal progress, the costs incurred are equivalent to those of a major, large-scale reclamation project.Ibrahim Nafiz
The second phase of the land reclamation and coastal protection project in GDh. Madaveli has been awarded to the Maldives Transport and Contracting Company (MTCC) for MVR 174 million.
In a ceremony held at the Ministry of Housing, Land, and Urban Development on March 8, 2026, the project agreement was signed by the Minister of Construction and Infrastructure, Dr. Abdulla Muththalib, on behalf of the government. Managing Director Ahmed Saudi signed the agreement on behalf of the Maldives Transport and Contracting Company (MTCC).
MTCC has announced that 19.17 hectares of land will be reclaimed in Madaveli under this project.
Furthermore, the project scope includes the installation of 1,645 meters of revetment and 120 meters of groynes. The project, valued at a total of MVR 174.58 million, is scheduled for completion within 400 days.
MTCC noted that the land reclamation project will provide a permanent solution to the housing shortages facing Madaveli, a community with a population of approximately 2,000 people.
The company further stated that the coastal protection project will provide significant relief to the environmental challenges facing the island, particularly regarding the ongoing issues of erosion and tidal flooding.