R. Dhuvaafaru Road Development Project, Phase Two
R. Dhuvaafaru Road Development Project, Phase Two
MTCC
Dhuvaafaru Road Develepment Project
Dhuvaafaru Road Develepment Project's second phase is well underway
The company has now commenced asphalt works
82 percent of the construction of major roads at Dhuvaafaru is now completed
The project is valued at MVR 37.8 million

Maldives Transport and Contracting Company (MTCC) states that the second phase of R. Dhuvaafaru Road Development Project is well underway.

MTCC shares that 82 percent of the construction of major roads at Dhuvaafaru is now completed. As such, the company has now commenced asphalt works on 17,790 sqm of roads on.

The scope of R. Dhuvaafaru Road Development Project involves, construction of nine roads with a total length of 17,790sqm; sidewalks of 6,923sqm; a carriageway of 17,790sqm; installation of storm water management system, road lighting and road markings.

The project is valued at MVR 37.8 million.