4 ސެޕްޓެމްބަރު 2026 | ހުކުރު 15:03The Dhaalu Hulhudheli land reclamation project has come to a complete standstill following the breakdown of an excavator brought in to commence the works, according to the island council. Despite the project being a key pledge made by President Muizzu ahead of the parliamentary elections, the council expressed deep concern over the lack of physical progress on the site.

Hulhudheli Council President Ahmed Nasru stated that flags were initially installed to demarcate the land reclamation area in Dhaalu Atoll Hulhudheli; however, those flags have since been blown down by strong winds. | raajjemv
The President of the Hulhudheli Island Council, Ahmed Nasru, has stated that flags erected to demarcate the land reclamation area ahead of the local council elections have since been blown down by the wind.
In an interview with RaajjeTV, Nasru stated that only a single excavator and a pickup truck were brought in for the project, and that work was carried out for just one night. He further noted that the excavator brought to the site is currently broken down.
Flags were put up across the island to coincide with the local council elections, but they have since fallen and been swept away. The only equipment brought to the island for the project was a single pickup truck and an excavator. The excavator remains stranded here simply because its engine is broken. In reality, work was only carried out for a single night.Ahmed Nasru
Nasru stated that the employees' only responsibility was to take a photograph that included the excavator. He further noted that no actual work had been assigned to the staff.
The Hulhudheli land reclamation project was a pledge made by President Dr. Mohamed Muizzu ahead of the parliamentary elections. At the time, President Muizzu stated that physical work on the project is scheduled to commence in July 2026.