14 Sep 2022 | Wed 16:38
Sh. Komandoo shore protection rectification and Mathi-Komandoo connectivity project
Sh. Komandoo shore protection rectification and Mathi-Komandoo connectivity project
MTCC
Sh. Komandoo shore protection rectification
Second shipment of rock boulders delivered to Sh. Komandoo
 
The shipment was delivered to the project site on 13 September 2022
 
The company will be doing shore protection rectification of 1,690m
 
The value of the project is MVR 249.90 million

Maldives Transport and Contracting Company (MTCC) has delivered the second shipment of rock boulders to Sh. Komandoo.

MTCC disclosed that this shipment of rock boulders are for the Komandoo shore protection rectification and Mathi-Komandoo connectivity project.

The shipment was delivered to the project site on 13 September 2022.

Under the project, MTCC will be doing reclamation operations of 16.7 hectares and connecting Komandoo and Mathi Komandoo with a 200m link.

The company will also be doing shore protection rectification of 1,690m.

The value of the project is MVR 249.90 million.