Lh. Kurendhoo shore protection project
Lh. Kurendhoo shore protection project
MTCC
Lh. Kurendhoo shore protection project
2nd shipment of rock boulders required for Kurendhoo shore protection delivered
The value of the project is MVR 44.92 million
Breakwater construction is currently underway at the project site
The shipment of rock boulders was delivered to the project site on 11 September

Maldives Transport and Contracting Company (MTCC) has delivered the second shipment of rock boulders required for the Lh. Kurendhoo shore protection project, to the project site.

MTCC disclosed that the shipment of rock boulders was delivered to the project site on 11 September.

The company highlights that the breakwater construction is currently underway at the project site.

Under the project, MTCC will be doing beach filling work of 91,000cbm, construction work of a 361m breakwater and a 822m revetment.

The value of the project is MVR 44.92 million.