MTCC states that the third shipment of rock boulders required for Maalhos Harbor Development Project has been delivered
MTCC states that the third shipment of rock boulders required for Maalhos Harbor Development Project has been delivered
MTCC
A.A. Maalhos Harbor Development Project
Maalhos Harbor Development Project well underway
The project is to be completed within 360 days
The project was mobilized on March 30
The value of the project is at MVR 56.9 million

Maldives Transport and Contracting Company (MTCC) disclosed that A.A. Maalhos Harbor Development project is well underway.

MTCC states that the third shipment of rock boulders required for Maalhos Harbor Development Project has been delivered to the project site on 16th April 2022.

Maalhos Harbor Development Project is valued at MVR 56.9 million.

The project includes work on dredging and excavation operations of 24,335cbm, construction of a 394m quay wall, a 407m breakwater, a 100m revetment, as well as few other works

Additionally, the company will be doing work of 1970sqm harbor pavement, construction of a ramp and installation of harbor lights.

The project is to be completed within 360 days and was mobilized on March 30.