Addu Bridge: Project pledged by President to commence within first 100 days remains stalled despite expiration of multiple government-imposed deadlines
28 ނޮވެމްބަރު 2026 | ހޮނިހިރު 10:42Ahmed Didi, the Member of Parliament for the Maradhoo constituency, has expressed concern over the delays in commencing the physical works of the Addu Bridge project despite it being awarded to multiple companies. While a Chinese firm has currently been tasked with the survey and design phases, the bridge remains one of the most significant development pledges made by President Dr. Muizzu’s administration to Addu City.


Chinese company contracted to conduct survey and design for Hithadhoo-Hulhumeedhoo bridge project | Social Media
Ahmed Didi, the Member of Parliament for the Maradhoo constituency, has expressed concern over the delays in commencing the bridge project intended to connect Hithadhoo and Hulhumeedhoo in Addu City.
Speaking on RaajjeTV’s "Vaudhunaama" program, MP Didi stated that one of President Dr. Mohamed Muizzu’s most significant pledges to Addu City is the construction of a bridge connecting Hithadhoo and Hulhumeedhoo.
However, MP Didi noted that even as President Muizzu’s administration enters its third year, work on the bridge has yet to commence. He further criticized the government, alleging that projects are merely awarded to various parties to coincide with elections.
One of the most significant pledges, for instance, the bridge project, has seemingly vanished from President Muizzu’s rhetoric. Over the past three years, the project has been repeatedly awarded to different contractors just ahead of elections; it was awarded to one party prior to the parliamentary elections, and similarly handed over to another group before the last council elections. While it was initially stated that physical work would commence before the end of 2024, the timeline has now shifted, with claims that the project will begin before the end of 2025.Ahmed Didi
MP Didi stated that the current situation reflects a complete lack of progress on any initiatives, leaving the public in a state of despair.
Initiating the construction of a bridge connecting Hithadhoo and Hulhumeedhoo in Addu City was scheduled for the final week of President Dr. Mohamed Muizzu’s first 100-day roadmap. In line with this, the government has announced that efforts are underway to contract a Chinese firm in January 2024 to conduct the feasibility study for the 15-kilometer bridge.
On February 19, 2024, the government contracted the Egyptian firm "The Arab Contractors" to conduct the survey and design for the Addu Bridge project, with the company providing these services free of charge.
Subsequently, in March 2024, President Muizzu announced that the feasibility study for the Addu bridge had been completed and that preparations were underway to begin physical construction.
However, Minister of Infrastructure Dr. Abdulla Muththalib stated that the company failed to progress the project to the stage of physical works, despite completing the bridge survey and reaching the proposal phase, as they were unable to secure the necessary financing.
The survey and design work for the bridge was awarded to China's TYLin International Engineering Consulting Company on October 25, 2025. According to the Ministry of Construction and Infrastructure, the scope of the agreement includes conducting site surveys, developing the bridge design, providing technical consultancy, and preparing the necessary documentation for the tendering process.
Furthermore, the Ministry of Infrastructure has stated that the concept design and review process for the bridge project commenced in March 2026.