Mandhoo Harbor Development Project is currently seeing 73 percent project progress
 
Currently ongoing at the site is harbor pavement installation work
 
The quay wall construction work under the project has been completed

Maldives Transport and Contracting Company (MTCC) has disclosed that the work on design and build of Harbor Development Project of Mandhoo island of Alifu Dhaalu atoll is well underway.

MTCC states that the Mandhoo Harbor Development Project is currently seeing 73 percent project progress.

The company notes that currently ongoing at the site is harbor pavement installation work.

Furthermore, the quay wall construction work under the project has been completed.

MTCC is required to dredge and excavate 65,854 cubic meters, construct a quay wall measuring 236 meters, a breakwater measuring 319 meters and a 71-meter revetment under the scope of the project.

The project also includes the construction of a 50-meter groyne, installation of harbor streetlights and navigational aids.

Further, a 1,180 square-meter pavement will also be constructed under the scope of the project.

The project is valued at MVR 34.1 million and was contracted to the company on 10 December 2019.