K. Male'
|
06 Jun 2023 | Tue 17:00
Kurinbi Harbor Development
Kurinbi Harbor Development
MTCC
Kurinbi Harbor Development
Kurinbi Harbor Development Project site mobilized
The value of the project is MVR 40.56 million
The project was mobilized on 4 June, 2023

Maldives Transport and Contracting Company (MTCC) has mobilized the Harbor Development Project of Kurinbi island in Haa Dhaalu atoll.

The project was mobilized on 4 June, 2023.

Under the project, MTCC will be doing new harbor basin dredging operations of 30,172 cubic-meters, existing harbor basin dredging operations of 4,389 cubic-meters and existing harbor entrance channel dredging operations of 2,040 cubic-meters.

The company will also be doing construction of a 295 meter breakwater; a 70 meter revetment; a 314 meter quay wall, as well as a ramp, an access platform and paving works measuring 1,556.61 square-meter.

Furthermore, MTCC will be installing harbor lights as well.

The value of the project is MVR 40.56 million.