Sh. Komandoo Shore Protection Rectification and Mathi-Komandoo Connectivity Project
Sh. Komandoo Shore Protection Rectification and Mathi-Komandoo Connectivity Project
MTCC
Maldives Transport and Contracting Company
Full shipment of rock boulders for Komandoo projects delivered
 
The company will be connecting Komandoo and Mathi Komandoo with a 200m link
 
The company will be doing shore protection rectification of 1,690 meters
 
The value of the project is MVR 249.90 million

Maldives Transport and Contracting Company (MTCC) has delivered the full shipment of rock boulders required for the ongoing projects in Komandoo Island of Shaviyani atoll.

MTCC on 28 May, disclosed that the company has delivered the full shipment of rock boulders required for the Komandoo Shore Protection Rectification and Mathi-Komandoo Connectivity Project.

Furthermore, the company stated that the existing revetment rectification work has reached 52 percent completion.

Under the project, MTCC will be doing reclamation operations of 16.7 hectares and connecting Komandoo and Mathi Komandoo with a 200m link.

The company will also be doing shore protection rectification of 1,690 meters.

The value of the project is MVR 249.90 million.