Hanimaadhoo harbor development project
Hanimaadhoo harbor development project
MTCC
Hanimaadhoo harbor development project
MTCC completes Hanimaadhoo harbor development project
The Ministry of Planning awarded the project to MTCC on 24 September 2019
The project was valued at MVR 64.6 million
MTCC disclosed this via twitter, on Sunday

Maldives Transport and Contracting Company (MTCC) has completed the harbor development project in Hanimaadhoo island in Haa Dhaal atoll.

MTCC disclosed this via twitter, on Sunday.

Under the scope of the project, MTCC dredged a new harbor basin up to 53,522.50 cubic meters, and a harbor entrance channel of 31,575.50 cubic meters.

MTCC also constructed a breakwater measuring 355 meters, a revetment measuring 50 meters and a 270-meter quay wall.

Further, the company installed 2,583 square meters of pavement, under the project.

The project was valued at MVR 64.6 million.

The Ministry of National Planning, Housing and Infrastructure awarded the project to MTCC on 24 September 2019.