Raajje.mv
Raajje.mv
  • ރާއްޖެ
  • ދުނިޔެ
  • ކުޅިވަރު
  • ވިޔަފާރި - އިގްތިސާދު
  • ސިއްހަތު
  • ރިޕޯޓު
  • ފިލްމް - މިޔުޒިކް
  • ތަފާތު ޚަބަރު
  • އިސްލާމް
  • ލައިފް ސްޓައިލް
localMaldives Transport and Contracting Company

MTCC completed 10 projects during Q2

31 ޖުލައި 2022 | އާދީއްތަ 09:13

The company took on 13 additional projects during the second quarter

ފާތިމަތު އުދުމާ
Fathmath Udhma | 31 ޖުލައި 2022 | އާދީއްތަ 09:13
Maldives Transport and Contracting Company (MTCC) has completed 10 projects during the second quarter of 2022

Maldives Transport and Contracting Company (MTCC) has completed 10 projects during the second quarter of 2022

Maldives Transport and Contracting Company (MTCC) has completed 10 projects during the second quarter of 2022.

MTCC states that the company managed a total of 115 projects during the second quarter. These included construction of harbors, airports and roads, as well as shore protection, causeway protection, dredging and reclamation projects.

Out of these projects, 10 projects were successfully completed and work on 12 projects were commenced.

Construction of R. Angolhitheem harbour upgrading works, completed on April 28, 2022. Under this project, MTCC completed dredging, construction of quay wall, breakwater, construction of groyne, harbor pavement, construction of ramp and installation of harbor streetlights.

Design and build of A.A. Ukulhas quay wall and jetty was completed on May 01, 2022. This project included dredging, construction of quay wall, revetment construction, construction of harbor pavement, construction of jetty, walkway bridge, as well as installation of streetlights and navigation aid.

The upgrading of K. Girifushi harbor was completed on May 05, 2022. Under this project, MTCC completed construction of a combined 314m breakwater in three different profiles.

Harbor redevelopment and reclamation project of K. Dhoonidhoo was completed on May 08, 2022. This project included harbor dredging, channel dredging, construction of quay wall, breakwater, sand filled breakwater, revetment, groyne, harbor pavement and installation of streetlights. The project also included construction of concrete walkway and a ramp. MTCC also fixed mooring buoys under the project.

MTCC completed the design and build of harbor in Th. Guraidhoo on May 09, 2022. This project also included harbor dredging, channel dredging, construction of quay wall, breakwater, sand filled breakwater, revetment, groyne, harbor pavement and installation of streetlights. The project also included construction of concrete walkway and a ramp. MTCC also fixed mooring buoys under the project.

Design and build of shore protection structured at V. Rakeedhoo was completed on May 25, 2022. Under this project, MTCC completed swimming area development works, constructions of breakwater, revetment and groyne.

Design and build of shore protection structures at V. Fulidhoo was completed on May 31, 2022. Followed by the Nakacha Hura reef dredging project on June 1, 2022.

K. Kudagiri picnic island reclamation and shore protection project completed on June 04, 2022 included reclamation and groyne construction.

MTCC completed the land reclamation and shore protection of R. Dhuvaafaru on June 06, 2022.

The company took on 13 additional projects during the second quarter.

MTCC

Popular

1

Eight Days Since Friend 4 Capsizing; Search for Missing Maldivians Continues

2

MNDF: Friend 4 Lies More Than 1,600m Deep, Beyond Military Submarine Reach

3

US Warns Maldives Over Circumventing Tariffs on Chinese Goods

4

State Minister Latheef of Sports Ministry abruptly dismissed from post

5

Widespread adverse weather expected across Maldives over the next 24 hours; wave heights to reach 6 feet!

More from Raajje.mv

03 އޮކްޓޯބަރު 2025

MTCC submits case to probe shareholders’ fund mismanagement

03 އޮކްޓޯބަރު 2025
MTCC submits case to probe shareholders’ fund mismanagement
17 އެޕްރީލު 2025

MTCC towers case: charges filed at PG against five

17 އެޕްރީލު 2025
MTCC towers case: charges filed at PG against five
15 އެޕްރީލު 2025

Minister confesses taxi drivers were not directly consulted on introducing taxi line

15 އެޕްރީލު 2025
Minister confesses taxi drivers were not directly consulted on introducing taxi line
15 އެޕްރީލު 2025

Gov’t guarantee to taxi drivers dissolves into thin air

15 އެޕްރީލު 2025
Gov’t guarantee to taxi drivers dissolves into thin air
28 ފެބުރުއަރީ 2025

Corruption case against MTCC Chairman under investigation

28 ފެބުރުއަރީ 2025
Corruption case against MTCC Chairman under investigation
30 ޖެނުއަރީ 2025

Pres. Muizzu unveils Hoarafushi Halfway House, established during Solih's administration

30 ޖެނުއަރީ 2025
Pres. Muizzu unveils Hoarafushi Halfway House, established during Solih's administration
02 މެއި 2024

AA. Himandhoo shore protection project site mobilized

02 މެއި 2024
AA. Himandhoo shore protection project site mobilized
20 އެޕްރީލު 2024

MTCC contracted HA. Dhidhdhoo Airport development project

20 އެޕްރީލު 2024
MTCC contracted HA. Dhidhdhoo Airport development project
08 އެޕްރީލު 2024

MTCC mobilizes GA. Kolamaafushi land reclamation project site

08 އެޕްރީލު 2024
MTCC mobilizes GA. Kolamaafushi land reclamation project site
04 ފެބުރުއަރީ 2024

Kudafari shore protection project reaches 52 percent progress

04 ފެބުރުއަރީ 2024
Kudafari shore protection project reaches 52 percent progress
ރާއްޖެދުނިޔެކުޅިވަރުވިޔަފާރި - އިގްތިސާދުސިއްހަތުރިޕޯޓުފިލްމް - މިޔުޒިކްތަފާތު ޚަބަރުއިސްލާމްލައިފް ސްޓައިލް
RaajjeMV
RaajjeTV
Raajje Sport
RaajjeTV Live
RaajjeTV PR
RaajjeMV
Raajje.mv

Copyright © 2010-2025 Raajje Television Pvt Ltd.

All rights reserved

ޕްރައިވެސީ ޕޮލިސީކިޔުންތެރިންގެ ހިޔާލުޓާމްސް އޮފްޔޫސް